|
| |

Building Bridges - Local manufacturer
assembling new Harlem River bridge
Danny Gist and several of his G&G Steel employees have spent
the past few weeks on the Gulf of Mexico coast in Mobile. But it has been far
from a pleasure trip. While many visitors to the Mobile area have been enjoying
warm temperatures and the beach, Gist and his 15-member crew have been busy
assembling a 364-foot-long bridge.
"We're getting very close to having everything in place,''
said Gist, owner of G&G Steel of Russellville. "This has been a major project
for us. It's been the largest project of this type that we've ever been a part
of.'' Once the assembly is completed, the bridge will be shipped by barge to
New York City and will ultimately span the Harlem River. The Third Avenue
Bridge will be 54 feet high and 88 feet wide. The four-lane structure will carry
thousand of motorists between the Bronx and Harlem daily. It is also a direct
link to famed Yankee Stadium. Components for the bridge were manufactured at
the Russellville plant and G&G's sister company, Warrior River Steel, in
Cordova.
Danny Gist said his company is a sub-contractor for the project. He said it's
the first time the company has done a project of this type, which includes the
manufacturing, assembly and delivery of the bridge. Jason Gist, one the key
players in the project for G&G Steel, said it took nearly a year to complete
manufacturing for the project. Once the parts were manufactured, they were
shipped by truck and barge to the Mobile-Chickasaw Port, just north of Mobile,
for the assembly.
Faye Tompkins, a G&G spokeswoman, said 43 tractor truckloads of parts were
shipped to the port. "And that's not counting smaller trucks or what was taken
by barge,'' she said. Jason Gist said inspectors have been on site with the
crew to oversee assembly. They were also involved during the manufacturing
process. He said G&G is nearing completion of its role in the project. "Within
the next week, everything should be on the barge and getting ready for the trip
to New York,'' Jason Gist said.
The bridge, which weighs 1,900 tons, is being assembled on an ocean-going
barge. Once the assembly is complete, the bridge will be floated around the tip
of Florida and then moved along the East Coast to the Manhattan side of the
Harlem River. It will be anchored between the existing Third Avenue Bridge and
the Willis Avenue Bridge until it is put in place in November 2004. Danny Gist
said it will take 10-14 days to ship the bridge to New York City. "We're
responsible for it until it gets there,'' he said. He said
Kiska Contractors of New
York is the general contractor on the project and will install the bridge.
"They'll take the old bridge down and float it out on a barge and then put the
new one in place,'' he said.
Company officials said this is the fourth time the bridge has been replaced. The
first bridge was built in 1797, the second in 1868 and the third in 1898. A
rehabilitation project followed in the 1950s. "This has been a challenge for
us,'' Gist said. "But we're proud of the product we've assembled.''
Above
article by By Tom Smith -
Regional Bureau
Third Avenue's New Swing Bridge
New York City definitely got its money's worth on this one.
Bridging 3rd Ave. at 129th St. with the Bruckner Blvd. in the Bronx, the
Third Avenue Bridge cost roughly $1.8 million to build
before it opened on August 1, 1898. Now, over 100 years later, the cost of the
replacement bridge over the Harlem River is weighing in at roughly $118 million.
This new Third Avenue bridge is actually
the fourth bridge at this location. The first was constructed in 1797 as a
power-producing dam for nearby mills. In the center of the structure was a
24-foot-long span with 12 feet of draft. This bridge/dam structure became a key
link connecting Manhattan to Boston via the Boston Post Road.
The second Third Ave. bridge opened 70
years later and lasted a mere 30 years. Made of cast and wrought iron, it
featured a 218-foot-long swing span, two 80-foot-wide navigable channels and a
52-foot-wide roadway. Repairs on it were frequent because of cracking of the
cast iron pier cylinders, splitting of the cast iron turntable wheels and more.
Ultimately deemed an obstruction to navigation, the Secretary
of War ordered a new bridge to increase the span of the draws and to raise the
bridges to a clear height of 24 feet above high water. The bridge was rebuilt in
conjunction with a massive Army Corps of Engineers project that reconstructed
the north end of the Harlem River, providing a navigable shipping channel
between the East River and the Hudson River.
On August 1, 1898, the third
Third Avenue Bridge opened. Featuring a 300-foot-long draw
span and two 102-foot-wide channels, when closed the bridge permitted 25 feet of
vertical clearance.
The initial deck carried two trolley tracks, which were
eliminated in 1928 during a reconstruction effort to accommodate automobiles.
The center of the bridge later served as a pathway for the Third
Avenue 'El' (elevated subway), until the line's demise in 1953.
Major reconstruction in the mid-1950s reconfigured the bridge
from four trusses (three deck sections) to three trusses with two roadways of
two lanes each. Until June when it was cut up and lifted out with barge-mounted
cranes, upwards of 76,000 cars per day crossed the span.
The project is divided into five stages of work and is
scheduled for completion in the spring of 2005. After a notice to proceed in
July 2001, "it took us [almost] three years to do the first half of the job,"
says Paul Connolly, project manager for designer Hardesty & Hanover of New York
City. "We'll do the second half in five months."
Long Island City-based Kiska Construction is the general
contractor on the project, working under NYCDOT financial incentives and
disincentives. If the roadway is completed ahead of schedule, Kiska is eligible
to receive a maximum of $4.875 million. As a disincentive, the penalty can be
from $25,000 to $37,500 each day the milestone date is exceeded with no set
maximum penalty.
The new swing span, manufactured in Russellville, Ala., by G &
G and floated up in July, consists of a through truss with sealed box members.
It is approximately 350 feet long and carries five, 12-foot traffic lanes and
two, 8-foot sidewalks — a total width of approximately 88 feet out-to-out. The
week of July 12 the new span was transferred from the single ocean-going barge
to two river barges.
Currently moored just south of the bridge crossing, work
includes installing electrical and mechanical systems, the control house, and
the roadway grating. Concurrently, the center pier and the south half of the
rest piers are to be completed. Kiska is also building new side piers and
modifying the center pier, to comply with seismic code, including the addition
of 10 new drilled-shaft support columns. Channel width clearances will increase
as well.
The next phase will include the float-in and connection of the
new swing span from its mooring in the Harlem River. Come November, Kiska will
use hydraulic jacks to lift the new span a few inches over the center and side
piers. Then as the tide recedes, the span will be guided into place, bolted down
and topped with a concrete deck. The float-in will also involve a full Harlem
River channel closure and Third Avenue roadway closure for
one weekend.
"By the end of the year, all five lanes of traffic should be
open," says H & H's Connolly. "It should be pretty exciting."
After the new swing span opens to vehicular traffic, the final
stage will including demolishing the temporary bridge and making the swing span
operational for river traffic. Complete reconstruction of the Bruckner Boulevard
approach ramps and all marine work associated with the new bridge, such as
fenders and navigation lights, will also be complete.
The Harlem River flows 8 miles between the East River and the
Hudson River, separating the borough of Manhattan from the Bronx and Queens.
Part of the current course of the Harlem River includes the Harlem Ship Canal.
Crossed by 14 bridges, it has more bridge crossings than any other waterway in
New York City.
The current inventory that crosses the Harlem starts in the
year 1848 with the completion of the High Bridge at West 174th St., ranging all
the way to the Alexander Hamilton Bridge at 179th St., which opened in 1963.
The DOT owns and operates eight movable bridges over the
Harlem River and continues its more than one-half-billion-dollar investment in
the bridges. The reconstructed Macombs Dam Bridge opened to traffic as scheduled
in March 2003. The DOT also has completed reconstruction of the University
Heights Bridge and the Madison Avenue Bridge.
The 145th Street Bridge is scheduled for reconstruction
between July 2004 and September 2007 at an estimated cost of $85 million. This
project will include the complete replacement of the swing span and six approach
spans, seismic retrofitting, partial reconstruction of substructures, and the
reconstruction of the approach roadways. In addition, the center median and
swing span center truss will be eliminated and standard lane widths will be
provided in each direction.
The remaining Harlem River Bridges, the Broadway Bridge, the
Wards Island Pedestrian Bridge, and the Willis Avenue Bridge are scheduled for
future reconstruction.
Some information provided by Steve Andersen (nycroads.com).
Above
Constructioneer article by By Matthew Phair
Spanning the Future
Thirty years ago, G&G Steel was a small firm with seven
employees. Today it employs more than 100 workers and is one of the largest
steel fabricators in the United States. The firm brought that experience to
bear when it recently completed work on a state-of-the-art bridge in one of
the world’s busiest cities.
Business
Bret Gist only has to go
through one traffic light to get to his job in
Russellville, Alabama. While his morning commute in this rural town of
10,000 people is simple, his business is not.
Gist and his family own G&G Steel, a
fabrication and manufacturing company that’s just completed work on a
sophisticated new bridge for one of the world’s busiest cities. The
Third Avenue Bridge spans New York City’s Harlem River, a 13-kilometre
tidal straight that separates the city from the boroughs of the Bronx
and Queens.
There are 14 bridges crossing the Harlem
River. All of them can open up to let ships pass through, but the Third
Avenue Bridge is special: When it opens, it swings.
Engineering enthusiasts admire swing
bridges such as the Third Avenue Bridge because of their unique design.
Imagine a bicycle tyre lying on its side: The bridge has an axle in the
middle of its span. The axle, placed in the middle of the river, will
rotate just like the bicycle tire – only horizontally – so it can swing
open. The bridge carries five lanes of traffic, and more than 70,000
cars cross it every day.
One of the largest
steel fabricators in the United States, G&G Steel has a
history of doing jobs for the United States Army Corps of Engineers,
including working on locks and dam gates. It has also done extensive
work for steel mills, aluminium mills and concrete industries. G&G Steel
has been in business since 1974, when Gist’s father, Danny, started the
firm with just seven employees. Today the company has 140 workers and a
28,000-square-metre facility.
"We’ve handled large movable systems, so
we were well suited for this bridge, rather than working on a fixed-span
bridge," says Gist. He says the company plans on doing further work with
heavy, movable systems and especially wants to tackle more bridge
projects.
In the Third Avenue Bridge, the entire
2,700 tons of the bridge will rest on a single spherical roller thrust
bearing situated at its centre, which was designed and manufactured by
SKF.
"This bearing type has been used for
swing bridges, but my understanding is that it is the largest one that’s
been used so far," says John Gimblette, senior project engineer for the
bridge’s design firm, Hardesty and Hanover in New York.
"We made the components that married the
bearing to the bridge," says Gist. "We have the expertise and highly
skilled workers. It’s very critical to be well versed and well trained
on how this machinery has to go together."
Hiring an all-in-one firm
such as G&G Steel made things easier for the New York
City Department of Transportation, which oversees the city’s bridges.
G&G Steel produced the drawings for the
bridge and began manufacturing the 111-metre-long structure in 2002.
Because of its extensive capabilities, it was also brought in on the
mechanical side of the project.
"We were able to fabricate it and
assemble it," says Gist. "Having complete capabilities made us a great
fit for the mechanical side of the project as well."
Those mechanical aspects were no small
matter.
The last time the bridge was replaced was in 1898. So it was more than
100 years later when the new bridge was installed, following months of
collaboration and innovation.
The old structure, says Gimblette, was a
rim-bearing bridge, so its load went down to multiple wheel assemblies
that rode on a circular track. The new bridge is based on the centre
pivot, meaning that the bearing takes the majority of the load.
Gimblette says that while the new bridge
was designed from scratch, the truss built by G&G Steel was designed to
look like the old one. "So, when you view it from afar, it will share
some of the same elements; it keeps some of that old world charm and is
aesthetically the same," he says.
Once the bridge was completed,
G&G Steel shipped the swing span truss to Mobile,
Alabama, loaded it on a barge and floated it around the Florida
panhandle and up the Atlantic Coast to New York. After its
2,900-kilometre journey, the structure was transferred to two river
barges and moored south of the old bridge. Work on the electrical and
mechanical systems, the control house and the roadway grating continued.
The bearing, meanwhile, was installed in G&G Steel’s Russellville
facility, then brought to Manhattan. It was floated into the middle of
the river and put on top of a pedestal. The new truss was then brought
in on barges and floated over the pedestal. The barges were sunk into
the river to lower the truss onto the pedestal.
"The SKF bearing was a very important
part of the job," says Gist. He points out that SKF is not new to the
company, since G&G Steel’s sister company, Franklin Manufacturing has
used SKF’s bearings in other projects for many years. The bearing also
features SKF’s NoWear coating, which protects the rolling surfaces to
greatly increase bearing service life.
"The NoWear coating is what sold the
engineers on having SKF be the ones to manufacture this bearing," Gist
says.
G&G Steel is currently working on another
bridge project in Manhattan – the 145th Street Bridge; the company has
been hired to fabricate, assemble and test all the mechanical aspects.
"The Third Avenue Bridge has opened up a different avenue for us," Gist
says.
Above
Evolution
article by Theta Pavis - Below Pictures by Mike Falco
YouTube Video
|